RCC-COL-M25-BLKA
RCC Columns M25 — Block A
Section A · Item 2
BOQ Qty
150.00
m³ contracted
Executed to date
68.73
m³ (45.8%)
Execution progress — Block A · RCC Columns M25
0 m³45.8% complete150 m³
All M-Books against RCC-COL-M25-BLKA
| M-Book | Pour Card | Element | Floor | Pour Date | Measured Qty (m³) | Status |
| MB-2026-018 | PC-018 | COL-A1-FL01 | FL-01 | 15 Jan 2026 | 0.235 | ✓ Approved |
| MB-2026-019 | PC-019 | COL-A2-FL01 | FL-01 | 15 Jan 2026 | 0.235 | ✓ Approved |
| MB-2026-028 | PC-025 | COL-A1-FL01 | FL-01 | 24 Mar 2026 | 18.31 | ✓ Approved |
| MB-2026-044 | PC-027 | COL-A1-FL02 | FL-02 | 13 Apr 2026 | 0.230 | ← This M-Book |
| Total executed to date: |
19.01 m³ |
of 150 m³ BOQ |
Note: Total executed quantity across all columns in Block A (all elements) = 68.73 m³ of 150 m³ BOQ. The above table shows only M-Books for element COL-A1-FL02 and related. Full BOQ execution is tracked in the BOQ Module.