M-Book Report

MB-2026-044 · Pour details, measurements & BOQ reconciliation

← Back to M-Book

M-Book Report

Velantra ERP · Tata Networking Hub · Generated 13 Apr 2026, 14:30

MB-2026-044
✅ QS Approved
Block A · FL-02
📒

M-Book Details

MB-2026-044
M-Book No.
MB-2026-044
Project
Tata Networking Hub
Block / Floor
Block A · FL-02
Source Pour Card
PC-2026-03-027
Element
COL-A1-FL02 · Column
Drawing
STR-COL-BLKA · Rev 2
BOQ Item Code
RCC-COL-M25-BLKA
Concrete Grade
M25
QS Assigned
R. Suresh
Status
QS Approved
Created On
14 Apr 2026
Approved On
15 Apr 2026
🪣

Pour Details — from PC-2026-03-027

Linked pour card
FieldPlannedActualStatus
Pour Date13 Apr 202613 Apr 2026✓ On schedule
Pour Start Time07:0009:102h 10m delayed
Pour End Time12:05✓ Logged
RMC Volume Ordered (m³)0.240.24✓ Exact
Actual Volume Poured (m³)0.240.24✓ Matched
No. of Truck Batches11
Slump (mm) — Truck 175–100mm90mm✓ Within range
Concrete Temp (°C)< 35°C28°C✓ Within limit
W/C Ratio≤ 0.500.45✓ OK
Cube Samples Taken2 sets (IS 456 Cl.15.2)2 sets✓ Compliant
Surface FinishAs specifiedAs-cast · Acceptable✓ OK
Curing StartedWithin 24h13:00 same day✓ Done
Client Engineer ApprovalRequiredA. Mehta · 07:45✓ Approved
📏

Measurement Book (No. × L × B × H)

CPWD / PWD Format
DescriptionNo.L (m)B (m)H (m)Qty (m³)Remarks
RCC Column — COL-A1-FL02
Block A · Grid A1 · FL-02 · M25
10.450.451.16 0.235 Partial pour · h = 1.17–2.33m
Deduct — Rebar void (est. 2%) -0.005 Standard deduction
Net Measured Quantity: 0.230 m³ BOQ unit: m³ · Rate: ₹8,950/m³
📊

BOQ Reconciliation

RCC-COL-M25-BLKA
RCC-COL-M25-BLKA RCC Columns M25 — Block A
Section A · Item 2
BOQ Qty
150.00
m³ contracted
Rate
₹8,950
per m³
Executed to date
68.73
m³ (45.8%)
This M-Book
0.230
Balance
81.27
m³ remaining
Execution progress — Block A · RCC Columns M25
0 m³45.8% complete150 m³
All M-Books against RCC-COL-M25-BLKA
M-BookPour CardElementFloorPour DateMeasured Qty (m³)Status
MB-2026-018PC-018COL-A1-FL01FL-0115 Jan 20260.235✓ Approved
MB-2026-019PC-019COL-A2-FL01FL-0115 Jan 20260.235✓ Approved
MB-2026-028PC-025COL-A1-FL01FL-0124 Mar 202618.31✓ Approved
MB-2026-044PC-027COL-A1-FL02FL-0213 Apr 20260.230← This M-Book
Total executed to date: 19.01 m³ of 150 m³ BOQ
Note: Total executed quantity across all columns in Block A (all elements) = 68.73 m³ of 150 m³ BOQ. The above table shows only M-Books for element COL-A1-FL02 and related. Full BOQ execution is tracked in the BOQ Module.
🧮

Summary

Measured Qty
0.230
m³ · This M-Book
Rate (BOQ)
₹8,950
per m³ · RCC Col M25
This M-Book Value
₹2,059
0.230 × ₹8,950
Cumulative Value
₹6.15L
68.73 m³ executed

Signatures

QS Approved
R. Kumar
Site Engineer
Submitted · 14 Apr 2026 · 08:30
R. Suresh
Quantity Surveyor
QS Approved · 15 Apr 2026 · 11:20
G. Kannan
Project Manager
Pending PM review